Cryogenic Storage Tanks

Project Information

Project Name

Butane Storage Tanks for Parsian Gas Refinery        (2 NO.’s)

Industry Branch

Design and Construction of Storage Tanks

Product(s) & Capacities

Capacity: 18000T/ Diameter : 45 M / Height : 32M

Type

Double Wall , Full Containment

Client

Palayesh Parsian Sepehr Company

Location

Mohr

Contract Scope

Process Design

√ 

Mechanical Design

√ 

Thermal Design

√ 

Basic Engineering

√ 

Detail Engineering

Procurement Services

 

Equipment & Material Supply

 

Fabrication

 

Construction

 

Pre-commissioning

 

Commissioning

 

Construction Supervision

Performance Test

Process Guarantee

Mechanical Guarantee

Contract Effective Date

1/6/2016

Contract Duration

6 months from the effective date

  • Project Information Project Name Butane Storage Tanks for Parsian Gas Refinery        (2 NO.’s) Industry Branch Design and Construction of Storage Tanks Product(s) & Capacities Capacity: 18000T/ Diameter : 45 M / Height : 32M Type Double Wall , Full Containment Client Palayesh Parsian Sepehr Company Location Mohr Contract Scope Process Design √  Mechanical Design √  Thermal Design √  Basic Engineering √  Detail Engineering √ Procurement Services   Equipment & Material Supply   Fabrication   Construction   Pre-commissioning   Commissioning   Construction Supervision √ Performance Test √ Process Guarantee √ Mechanical Guarantee √ Contract Effective Date 1/6/2016 Contract Duration 6 months from the effective date
  • Project Information Project Name Propane Storage Tanks for Parsian Gas Refinery        (2 NO.’s) Industry Branch Design and Construction of Storage Tanks Product(s) & Capacities Capacity: 18000T/ Diameter : 45 M / Height : 32M Type Double Wall , Full Containment Client Palayesh Parsian Sepehr Company Location Mohr & Assaluyeh Contract Scope Process Design √  Mechanical Design √  Thermal Design √  Basic Engineering √  Detail Engineering √ Procurement Services   Equipment & Material Supply   Fabrication   Construction   Pre-commissioning   Commissioning   Construction Supervision √ Performance Test √ Process Guarantee √ Mechanical Guarantee √ Contract Effective Date 1/6/2016 Contract Duration 6 months from the effective date